Friday, October 16, 2009
Drywall Delivery
Thursday, October 15, 2009
The Bathroom
Above is a look at the shell that we started with. This is pretty much where Contractor C and the plumber left us. Chad and I took it from here to remain within our budget. As some of you my know, the adventure of making a bathroom happen is VERY timely, overwhelming and pricey. This is basically why I am documenting this room specifically. Chad and I worked our bottoms off to make it happen.
This is after the drywall was hung.
Our first step was to tile the shower. We had never tiled before, so this was a lot of fun for us. I think the most frustrating thing about tile isn't that there are so many steps, it's that they all require a drying time of 24-48 hours!
We chose a white subway tile with a row of glass tiles as an accent. I still haven't been able to take a worthy picture of the glass tiles. They are natural colors with a shimmery copper throughout. They really warm up the white tiles.
Well, I am going to leave you in suspense of the final reveal pictures. But, I will leave you with this original picture of my two sink vanity. This was a true Cherokee Street find. Just wait until you see what a beauty it has become!
Friday, October 2, 2009
10 Years
Today is our 10 year marriage anniversary! It is just impossible to think that we have reached such a milestone. Not because it's been a long decade, but because I am a bit in shock that we are old enough to stake such a claim.
Our story is a bit unique for we were high school sweethearts! I was 15 when I first met Chad in our high school hallway, however, we didn't start dating until I was almost 17. I was a sophmore in high school and he was a freshman in college. After that we were pretty much inseparable. And, I still see us as a couple kids riding side by side in his 1967 plymouth fury. He'd drive to wherever I was almost every weekend and we'd talk for at least an hour every night on the phone. I am so Blessed to say that I married my Best Friend and that he is still my Best Friend today.
I look at the past decade and our little piece of history.....graduating, getting married, starting careers, traveling, job changes, losing my mom, buying a home, having a child, then having another, and now renovating...and it only makes me look forward to what the next decade will bring with my Best Friend by my side.
Here's to my "Sweet Boy!" You continue to ROCK my world!
Tuesday, September 29, 2009
Ava and Mommy
Monday, September 28, 2009
The New Master Suite
Sunday, September 27, 2009
The Original Attic
Here is a picture of what our attic originally looked like. The stairwell is off our Living Room and comes up in the center of the north side of the house. It was pretty much a large square room with a hard wood floor, brick walls, slopping ceilings and cruddy windows. It had great potential but was very dark.
The reason why previous homeowners had not renovated was because the upstairs floor was originally built with 2x6 joists and code today is 2x10. This meant that the entire wood floor had to be removed.....
....so that it could be reinforced with 2x10s from the front roof peak to the back. A very labor intensive job and a tricky feat since it meant exposing all the plaster keys and risking the chance of cracking/breaking our plaster ceilings below. This step seemed like an impossible feat and I envisioned gaping holes in my ceilings downstairs. I'm pleased to say that it went very well and we only have a few new cracks. Nothing that cannot be repaired or isn't expected in a plaster house built in 1936.All the old lumber and new lumber was hoisted in through the tiny window visible in the previous pictures.
A hole had to be cut in our back roof to set the beams directly on our exterior wall so that they would properly support the 19 ft. dormer.
Our stairwell leading downstairs.
A picture from the other side of the room facing the stairwell after the floors had been completed and plywood laid. The next step was the dormer. See my post from last July.
Saturday, September 26, 2009
Basement Stage 2
We had five new holes to dig and posts to set in the basement. It started out like this. Ignore the extra lines Contractor C got a little spray paint happy!
Then the boys got to work cutting and digging up the concrete AGAIN! I must say the dedication and hard work ethic the men in my family have just blows me away. They dug all these holes and had to remove all the cement/rock/mud in buckets out a tiny basement window! Unbelievable! Then the rebar was set.
Does this help put it into perspective? I couldn't get hole number 5 in the shot.
Then they had to fill the holes with cement. This job was so big that we rented a little Bob the Builder "Dizzy" cement mixer (it was really cute) and they built a shoot to drop in from outside. It was also quite impressive. Shout out to our friend Matt in Mobile, AL whose in the yellow. He and Chad had a very dusty and dirty job of mixing the cement outside.